Germany aims to plug hole in energy transition

Germany produces more power from renewable energies than ever, yet pushing dirty lignite out of the power market has proven to be a contentious issue. Steve Baragona summarizes the social, political and economic hurdles currently delaying a coal phase-out.

Lignite power plant Neurath

The green appearance can be deceiving: Germany’s Energiewende will have to cope with the role of lignite for power production in the near future. (Photo by TelepermM, modified, CC BY-SA 4.0)


As Germany executes what may be Europe’s most ambitious transition to clean energy, the dirtiest form of coal-fired power has held fast to a major share of the country’s power supply. Meanwhile, some of the most efficient gas plants in Europe are shutting down.

New legislation aims to correct the situation and bring the country’s greenhouse gas emissions in line with its climate targets. Critics call the measure a massive handout to the electric utilities. But it seems to mark a transition. Experts across the German power industry say the end of lignite coal is in sight.

Wind and solar power production has exploded since 2000, when the country passed its Renewable Energy Act. This year, a third of Germany’s electricity is expected to come from renewables.

But rather than replacing lignite coal — Germany’s largest, dirtiest and least-efficient source of fossil energy — it’s clean-burning gas that has taken the hit. “When you thought about energy transition some years ago, the gas-fired power stations were expected to be the perfect partners of renewables,” said Vera Bueke, spokeswoman for the utility company RWE.

Gas plants can be switched on and off quickly in response to fluctuations in supply from wind and solar, she explained. And they produce the least CO2 of the fossil facilities. “But in fact, they are kicked out of the system because the power prices now are so low,” she added.

Cheap electricity

Solar panels and wind turbines produce electricity for next to nothing. There’s no fuel to buy and no plant operators’ salaries to pay, so the electricity they produce is the cheapest available on the wholesale market.

And Germany has abundant domestic supplies of lignite coal. So power plants burning locally-mined lignite can produce electricity for roughly half the cost of gas. Europe’s carbon-emissions trading system was supposed to price CO2-intensive lignite out of the market. But carbon prices are too low, and falling. Last year, prices were less than half what they were in 2009.

Marginal Cost of old lignite and new gas power plants

With demand drying up for relatively expensive natural gas-fired power, utilities have been closing or mothballing many of their plants — including ones they just built a few years ago. In March, German utility E.ON announced plans to idle a highly efficient gas plant that went online in 2010.

Persistence of lignite

Meanwhile, even as renewables have mushroomed, lignite coal has held on to roughly a quarter of the overall energy pie. The persistence of lignite threatens Germany’s climate goals. The country had committed to cut its greenhouse gas emissions by 40 percent from 1990 levels by 2020.

But “the government found that there was a gap,” said Patrick Graichen, head of the Berlin-based energy think tank Agora Energiewende. The country would fall short of its goal by 22 million metric tons of CO2.

Fuel Sources of German Electricity ProductionAdditional measure

“There was the clear need for some sort of additional measure or it would be clear that Germany wouldn’t be meeting its 2020 targets,” said Graichen. That measure, which the government approved Nov. 4, puts production at eight lignite power plants — about one-seventh of the country’s lignite capacity – on hold. At the end of four years, these facilities are to be shut down. The owners will receive 1.6 billion euros to keep the plants idle. Critics howled.

“They will never need this reserve. Never,” said Niklas Schinerl, a campaigner with Greenpeace Germany, noting the massive overcapacity on the German electricity market. “They just put it aside and give them, actually, a lot of money for doing nothing.”

“We had a better proposal,” acknowledged State Secretary Rainer Baake at the Federal Ministry for Economic Affairs and Energy. The government’s original plan was to charge lignite plants a fee for their high CO2 emissions.

But trade unions took to the streets in protest, claiming it would drive the plants and the mines that supply them out of business, cost 100,000 jobs and devastate coal-mining regions, especially in the former East Germany. The government relented. “There was not a majority for this proposal, so another decision was made,” said Baake. “In a democratic society, that has to be accepted.”

It may be better than the alternative, said Tilman Schwencke, director of strategy and politics at BDEW, Germany’s energy and water industry association. But, he added, “I think nobody likes the solution. Really, nobody.”. Especially since it provides no guidance on how the country will reach its goal of cutting its emissions by 80 percent by 2050.

“This is just for 2020,” he said. “It costs a lot, nobody’s happy, it has nothing to do with the market… It’s just, yeah, you shut it down, you get your money, we reach our target, full stop. So, that’s done. Now we have to think about how to do it in a different and more market-oriented way for 2050,” he added.

The beginning of the end of coal?

And by then, the government envisions a very different energy world. “In 2050, we are not going to [burn] lignite in Germany anymore,” Baake said.

He is fully aware that this will not be easy for the regions that depend on coal, acknowledging, “Of course, there is going to be a huge impact.”

The west of the country has chemical and other industries that may be able to ease the transition. But in the eastern region, he added, “there are not easy alternatives to be found. So, the transition is going to be more difficult in the east than in the west.”

The end of lignite coal is decades away, however. Experts say it won’t happen until there is a way to store more of the fleeting energy from wind and solar, and until Europe builds the connections necessary to link the places that need power to the windy and sunny places that produce it.

But there is a consensus across Germany that that day is coming. Perhaps most remarkably, even the miners’ union is talking about the end. Ralf Bartels, head of energy reform and sustainability for IG BCE, the union representing mining, chemical and energy workers, won’t put a date on it.

“There are a lot of people who are asking us, ‘When will it be? Can’t we exit lignite in [the year] 20-[something]?’” said Bartels. “And the answer I give them is, let’s talk about those [transmission] links. I wouldn’t like to throw a dice and say it’s 20-anything.” But, he added, “As soon as there is this grid, or as soon as there is this storage capacity, then we will shut it down.”

This article was first published on Voice of America and is republished with permission by the author. Steve Baragona (@stevebaragona) is an award-winning multimedia journalist covering science, environment and health. He spent eight years in molecular biology and infectious disease research before deciding that writing about science was more fun than doing it. He graduated from the University of North Carolina at Chapel Hill with a master’s degree in journalism in 2002. Baragona co-wrote a documentary on the impacts of the 2012 drought in the U.S. Midwest that won four awards.

by

The "Energiewende Team" has an administrative function. We use this account to repost all the best articles about the global Energiewende from around the web.

4 Comments

  1. heinbloed says

    About 17% of the hard coal power capacities weren’t available (unplanned outage) reading the 1st of December:

    https://blog.stromhaltig.de/2015/12/rhein-dampfkraftwerk-karlsruhe-voruebergehend-nicht-verfuegbar/#comment-1946

    Nature strikes back, after a new low water level record (134 days in one go) coal ran out at the German power plants along the river Rhine.

    Polish lignite companies can’t find easy money to finance the take-over of German mines and increasing the output in Poland:

    http://www.platts.com/latest-news/coal/warsaw/coal-power-plant-financing-harder-to-find-polands-26300754

    The point of sale is stretched further by lignite owner Vattenfall, envisaged is not anymore the first half of 2016 but mid-2016:

    http://www.rbb-online.de/wirtschaft/thema/2014/kohle/welzow/beitraege/umweltschuetzer-besetzen-bagger-in-jaenschwalde-und-welzow-sued.html

    One wonders how the existing damages of the cross-border ground water resources are to be included in the sale price …..

    http://www.rbb-online.de/wirtschaft/thema/2014/kohle/welzow/beitraege/polnische-Gemeinden-klagen-gegen-Vattenfall-Braunkohle.html

  2. Mikael says

    15 years and nothing has happened. It’s a very impressive “change”…

    Is the Energiewende the biggest environmental scam in the history?

  3. heinbloed says

    An Eastern German lignite mine closes, the last coal train will leave the open pit “Cottbus-Nord” on Wednesday:

    http://www.rbb-online.de/wirtschaft/thema/2014/kohle/welzow/beitraege/tagebau-cottbus-nord-ist-geschichte-braunkohle-lausitz.html

    http://www.rbb-online.de/wirtschaft/thema/2014/kohle/welzow/beitraege/vorbereitungen-ostsee-flutung-tagebau-cottbus-nord.html

    The substance is gone, no material exists for back-filling the 220 million tonnes taken out.
    The hole will be flooded from 2019 onward. This should take between 5 and 11 years.
    The supplied power plant Jaenschwalde (Germany’s dirtiest) will successively close down from 2018/2019 onward.
    ——————-
    Last week Friday Germany’s 3rd last hard coal mine “Auguste Victoria” closed with about 50% of Germany’s hard coal production, together with the colliery in Kellingley/UK :

    http://www.dw.com/de/das-aus-f%C3%BCr-die-steinkohle-r%C3%BCckt-n%C3%A4her/a-18924632

    http://www.independent.co.uk/news/uk/home-news/kellingley-colliery-miners-march-in-final-farewell-to-the-last-coal-mine-and-british-mining-a6780301.html

    RWE has given up on hard coal investments in Germany, the last power plant will stay unfinished and the scrap can be sold:

    http://www.reuters.com/article/rwe-coal-idUSL8N1472JT20151218

    Investors who joined RWE falling into this trap will be compensated by RWE with electricity vouchers (!) since there is no money left:

    http://www.iwr.de/news.php?id=30343

    Vattenfall’s lignite assets – to which the closed pit “Corttbus-Nord” belongs have lost € 1 billion – € 1.5 billion in value within a year:

    http://uk.reuters.com/article/vattenfall-germany-lignite-idUKL8N1471W020151218

    Every couple of month Vattenfall announces that the sale of their German assets will be ‘soon’ …. now they want bidders to turn up before Christmas:

    https://www.rbb-online.de/wirtschaft/thema/2014/kohle/welzow/beitraege/vattenfall-verkauf-braunkohle-angebote.html

    Waiting for another year won’t deliver anything anymore I’d say.
    Greenpeace wanted to be payed € 2 billions to take over responsibility for Vattenfall’s lignite assets:)